Projects List

Underground Blast Louvres

Industry: Resource/Mining

Scope: The site required a ventilation extraction system located in an underground workshop. This needed to be controlled either locally or remotely via SCADA from Mine Control in the event of a fire or emergency.

Works Carried Out:

  • Installation & configuring of modbus electric actuators
  • Installation & programming of Schneider M340 PLC
  • Programming and testing of CitectSCADA interface
  • Commissioning & site acceptance testing of the system

Paste Diversion Valves

Industry: Resource/Mining

Scope: The site required diversion valves for a Paste Reticulation System. This allowed any blockage events to be cleared efficiently by diverting to a designated sump & reduced the downtime between stope cures by allowing the flow to be diverted to the next available stope.

Works Carried Out:

  • Develop program using Schneider M340 PLC
  • Programming and testing of CitectSCADA interface
  • Commissioning & site acceptance testing of the system

Citect SCADA Upgrade

Industry: Resource/Mining

Scope: The site required an upgrade of the CitectSCADA system to allow for alarm management software & replacement of outdated infrastructure.

Works Carried Out:

  • Installation of Power Edge R440 Servers
  • Existing 7.2 Citect SCADA upgraded to 8.00 Update 37
  • Upgrade of all Citect licences
  • Integrated two separate projects utilising one pair of redundant servers
  • Site commissioning

 

Water Monitoring

Industry: Resource/Mining

Scope: Utilising SCADA packs on a licensed UHF system.

Works Carried Out:

  • Installation and programming of local HMI
  • Installation and programming of ScadaPack
  • Programming and testing of CitectSCADA interface
  • Commissioning & site acceptance testing of the system